Sl No | Project Scope | Participate Own / JV | Value of work awarded (Crs) | Work Completed (Crs) | Bills Received (Crs) | Bills Receivable (Crs) | Balance Work to be done (Crs) | Remarks |
---|---|---|---|---|---|---|---|---|
1 | Construction of bypass to Bagalur town branching from Km 3/0 (Kothapalli) and joining at km 9/350 (Jee Mangalam) including Shifting of Utilities of NH 207(New NH 648) on Engineering, Procurement & Construction (EPC) Basis Contract in the state of Tamilnadu-(Job No. NH-207 (New NH-648) - TN-2021-22-992) | CDR & Co Constructions | 58.94 | 25.00 | 14.86 | 10.14 | 33.94 | |
2 | Widening from Two lane with paved shoulder to four lane with paved shoulder and Strengthening in Km 0/8 – 17/6, 18/0 – 25/0, 25/500 – 27/900, 29/6 – 34/0 & Km 39/0 – 50/570 and strengthening in km 17/6 – 18/0, 25/0 – 25/5, 27/9 – 29/6, and widening from Four lane to four lane with paved shoulder and strengthening in km 34/0 – 39/0 including centre median in selected stretches, Construction of Storm water drain including Widening and Reconstruction of CD works and Additional Bridge at Km 39/8 of NH 532 (Cuddalore – Vridhachalam – Salem Road) | CDR-S&P (JV) | 267.00 | 150.00 | 130.49 | 19.51 | 117.00 | |
3 | Widening from Two Lane to Four Lane and Strengthening at Km 0/0 - 6/6 & 8/2 - 15/8 of Kallakurichi - Thiruvannamalai Road (SH-6) including Construction of Centre Median, Drain, Retaining Wall, Junction Improvement, Reconstruction of Culverts, Minor bridges, Major Bridge and Paver Blocks TVM-116 | CDR & Co Constructions | 104.55 | 82.00 | 67.16 | 14.84 | 22.55 | |
4 | 4 lane NH connectivity to ICTT Vallarpadam Stretch between Kalamassery to Vallarpadam section of NH-996A in the state of Kerala Clarification from Bidder | CDR & Co Constructions | 108.00 | 23.00 | 9.26 | 13.74 | 85.00 | |
5 | Periodical Renewal/Overlay in Madurai to Tuticorin section from Km 138/800 to Km 266/865 of NH-38 (Old NH-45B) in the State of Tamil Nadu on Item Rate Basis | CDR & Co Constructions | 144.56 | 12.00 | 4.64 | 7.36 | 132.56 | |
6 | Periodic Renewal Strengthening in Thanjavur to Trichy section from Km 80.000 to Km 128.480 of NH67 New NH83 in the State of Tamil Nadu on Item Rate Basis | CDR & Co Constructions | 33.18 | 0.00 | 0.00 | 0.00 | 33.18 | |
7 | Improvement and Up-gradation to two lane with Paved Shoulder/Four Lane configuration from existing Km 130.000 to Km 191.00 (design chainage Km 131.500 to Km188.735, design length 57.235Km) of NH-227A (near Barahalgani to Meharauna Ghat) in the state of Uttar Pradesh on Hybrid Annuity Model (HAM) basis | CDR & Co Constructions | 254.00 | 12.00 | 0.00 | 12.00 | 242.00 | |
8 | Forming and Improving Western Bypass road to Tirunelveli town branching from km 148/8 of NH 44 (Thazhaiyuthu) and ending at km 169/6 of NH 44 (Konganthanparai Vilakku) | CDR & Co Constructions | 110.00 | 0.00 | 0.00 | 0.00 | 110.00 | |
Total | 1080.23 | 304 | 226.41 | 77.59 | 776.23 |